Planning & Construction Updates

January 2018

Determination of Non-Significance (DNS): The Wing Luke Hearing Examiner issued findings, conclusions and decision recommendation to the Superintendent. The Superintendent has affirmed the DNS.


December 2017

This month, the Wing Luke project team completed SEPA activities and held an appeals hearing, continued construction document design work and met with the PTA at the school.


November 2017

Review of the Design Development documents budget was completed. Construction Document design work began. Contract negotiation were underway.


October 2017

Design Development completed. Design review continued. The SEPA Determination of Non-Significance was released and the decision was appealed.


August 2017

Design development continues and design review with stake holders has been completed. The Value Engineering and estimate reconciliation was completed. The Master Use Permit has been submitted to the City of Seattle.  


June 2017

Design Development and design review with stakeholders continues. The SEPA check list was completed and reviewed by the district. The value engineering kick-off meeting was held. Review of the project budget by a third party is nearly complete. Completed a design review with district maintenance team.


May 2017

Continued Design Development phase. Design review with stake holders is ongoing. Completed the SEPA checklist. Set Value Engineering meeting dates.


March 2017

Schematic Design was 70% to 75% complete. The School Board approved the contract with NAC Architecture. Project meetings continued. The topographical survey and the tree survey were completed. Geotechnical work was done. Design review continues. The SEPA Checklist activities were ongoing. 


Return to Wing Luke