BEX IV » Queen Anne » Planning & Construction Updates

Planning & Construction Updates

April 2018

  • Set date for Seattle Department of Construction and Inspections (SDCI) Departure Appeal Hearing
  • Prepared for Departure appeal hearing 
  • Reviewed preliminary Critical Path Method (CPM) schedule 


March 2018

  • Departure appeal period 
  • Held bid opening 
  • Began relocation coordination with school staff


February 2018

  • Finalized Certificate of Approval
  • Advertised to Bid
  • Published SDCI departure decision
  • Released Addendum No. 1
  • Completed pre-bid meeting


January 2018

  • The determination of non-significance (DNS) decision was affirmed
  • Advertised for bids
  • Completed and reconciled 95% construction estimate
  • Completed 100% construction documents


December 2017

  • The SEPA appeal hearing was held.
  • A contract for constructability review was signed
  • Project received conditional approval from Seattle Parks and Recreation to use Bigelow Avenue for school bus student drop-off/pick up.


November 2017

  • Building permit and land use departure was submitted to the City of Seattle.
  • The Construction Documents reached 75%
  • Consultant was selected for the constructability review.


October 2017

  • Published and advertised the SEPA Determination of Non-Significance (DNS).
  • Completed 50% of Construction Documents.


August 2017

  • The design development estimate was received.
  • The design development drawings set was completed.


June 2017

  • The SEPA public meeting was held to receive public comment.


May 2017

  • Reconciled Schematic Design Budget. Released SEPA for public comment.


March 2017

  • A school design advisory team (SDAT)meeting was held, and the project team had a pre-submittal meeting with the city.


February 2017

  • The conceptual design to develop was selected.


January 2017

  • The pre-submittal permit conference with the City of Seattle was held.
  • The team also met with Seattle City Light.


December 2016

  • SDAT meeting #7 was held.
  • School tours with Teaching and Learning staff took place.


November 2016

  • Held School Design Advisory Team (SDAT) meeting #7.
  • Conducted school tours for Teaching & Learning staff.


October 2016

  • The schematic design phase was kicked off and SDAT meetings were held.
  • The conceptual design was reconciled with the project budget.


Return to Queen Anne