Queen Anne

Recent Updates

Address: 2100 4th Ave. N., Seattle

Watch the Construction Camera

Overview

This building originally opened in 1905 and was recently modernized and reopened in 2011. An addition will increase the school’s capacity and add core facilities.

Budget

$16.4 million

Project Description

Build an addition with 200 seats of permanent capacity and a gymnasium to address current and projected elementary growth in Queen Anne and downtown Seattle, and reduce overcrowding at elementary schools in the area.

Design: Mahlum Architects
Construction: Hensel Phelps Construction

Schedule Overview

Estimated design work start: February 2016

Estimated construction start: June 2018

Estimated school opening: 2019


Back to BEX IV