BEX IV » McGilvra Lunchroom » Planning & Construction Updates and Photos

Planning & Construction Updates and Photos

August 2018

  • Site work 100% complete including punchlist items.
  • All work complete in main building including seismic work for earthquake safety, and reconfiguration of space to make two new flex spaces for art and music.
  • Lunchroom building complete with training started for onsite staff and facilities team.
  • Ribbon cutting event held Sept. 4


June 2018

Site:

  • Site grading occurring on north end of site.
  • Concrete site flatwork is 90% complete.
  • New fence has been installed.
  • Asphalt installation begins within next two weeks.

Main Building:

  • Seismic and new classroom work, including punch list, has been completed.
  • Demolition of existing kitchen completed.
  • Lighting installation underway in new classroom space.

Lunchroom Building:

  • Dining area concrete floor has been ground and polished.
  • Plastic laminate panels and casework installation is 75% complete.
  • Wall and floor tile is nearly complete.
  • Siding is being installed.
  • Landscaping to begin in July. 


April 2018

Site: 

  • Installed temporary fencing and established delivery access

Main Building: 

  • Completed all earthquake safety/seismic and new classroom work 
  • Completed punch list items

Lunchroom Building: 

  • Completed metal stud framing 
  • Installed steel stair up to mechanical mezzanine 
  • Installed masonry
  • Completed Mechanical | Electrical | Plumbing (MEP) rough-in
  • Started Z-Metal layout for installation of exterior siding 
  • Started window frame installation and glazing 


March 2018

  • Installed temporary fencing and established delivery access.
  • Completed main building seismic and new classroom work. 
  • Lunchroom Building: 
  • Completed metal stud framing.
  • Installed steel stair up to mechanical mezzanine 
  • Continued masonry work. 
  • Completing mechanical/electrical/plumbing rough-in. 
  • Started Z-Metal layout for exterior siding installation 
  • Began window frame installation and glazing. 


February 2018


January 2018


November 2017


September 2017


Return to McGilvra Lunchroom