BEX IV » Daniel Bagley » Planning & Construction Updates

Planning & Construction Updates

October 2018

  • Continued construction documents phase
  • Met with Bagley teachers to present 95% project design
  • Received first round of permit comments
  • Began constructability review


September 2018

  • Continued construction documents phase
  • Completed 65% construction document set updates


August 2018

  • Construction Documents phase in process.
  • Permit documents submitted to City of Seattle.


June 2018

  • The SEPA appeal was completed on June 25
  • The final Departures report was issued by the Seattle Department of Construction and Inspections


May 2018

  • SEPA appeal has been received; hearing scheduled for June 25
  • Coordinated final Seattle Department of Construction and Inspections (SDCI) departures report with city staff
  • Presented project to the Landmarks Board Architectural Review Committee on May 11


April 2018

  • Responded to all SEPA public comments and published Decision of Non-Significance (DNS) 
  • SDCI held Departures Committee meeting on 4/25 and obtained recommendation for approval on parking departure 


March 2018

  • Collected and compiled all public comments concerning the draft SEPA documents and the public meeting.
  • Presented the design to the Seattle Landmarks Board Architectural Review Committee. 
  • Prepared presentation material for the Departures meeting in April.


February 2018

  • Published draft SEPA documents; held public meeting on February 15
  • Completed Design Development phase
  • GC/CM has completed estimating and design is within the targeted budget
  • Prepared design update for the Landmarks Board Architectural Review Committee (ARC)
  • Prepared for the code departures process


January 2018

  • Integrated the draft SEPA checklist comments
  • Completed Design Development phase
  • General Contractor/Construction Management firm has started work on estimating
  • Prepared design update for the Landmarks Board Architectural Review Committee
  • Prepared for the code departures process


December 2017

  • The draft SEPA checklist was under district review.
  • The Design Development phase continued and a design update was prepared for the Landmarks Board Architectural Review Committee (ARC).
  • Preparations began for the code departures process.


November 2017

  • The project team completed the draft SEPA checklist.
  • Design Development continued.


October 2017

  • Contractors completed the draft SEPA checklist and prepared it for district review.
  • The Design Development phase of the project has begun, and a design update was prepared for the Landmarks Board Architectural Review Committee.


August 2017

  • The schematic design phase work and the schematic design value engineering have been completed.
  • The state Office of the Superintendent of Public Instruction-required value engineering effort has been completed.
  • Pre-construction work began including exploratory demolition and tree preparation.
  • The draft SEPA checklist was completed for review by district staff.


June 2017

  • The Schematic Design Phase work has been completed.
  • The general contractor construction manager(GCCM) started the pre-construction phase of work.
  • The Schematic Design Value Engineering effort is underway. Preparations for the SEPA checklist continue.
  • The first community open house was held at the school on June 6.


May 2017

  • Completed the Schematic Design Phase work.
  • Completed the procurement process for the General Contractor / Construction Manager (GCCM).
  • An interim contract was approved to start the preconstruction phase of work.
  • Schematic Design documents are being priced to evaluate the construction cost against the budget.
  • Preparation for the SEPA checklist continues.
  • The first community open house is scheduled for June 6at 6:30pm at the school.


March 2017

  • The Schematic Design Phase work was nearing completion.
  • The procurement process for the General Contractor/Construction Manager (GCCM) was nearly done.
  • Preparation for the SEPA checklist continued.
  • The pre-submittal conference for the Master Use Permit was held.


February 2017

  • The Schematic Design Phase work continued.
  • Site-Specific Educational Specifications were being refined.
  • Work on the transportation studycontinued.
  • The procurement process for the General Contractor/Construction Manager (GCCM) was underway.
  • Preparation for the SEPA checklist began.
  • The preliminary site plan for the classroom addition was well received at the Seattle Landmarks Preservation Board Meeting.


January 2017

  • The schematic design phase work continues.
  • The Site-Specific Education Specifications are being refined and the transportation study continues.
  • Preparation for the General Contractor/Construction Manager (GCCM) procurement process was nearing completion.


December 2016

  • The School Design Advisory Team (SDAT) process has been completed.
  • The schematic design phase work has begun.
  • Site-Specific Educational Specifications are being developed.
  • Work has begun on the transportation study.


November 2016

  • The School Design Advisory Team (SDAT) process was nearly complete.
  • The geotechnical report has been completed with the consultant comments incorporated.
  • Work began on the transportation study.


October 2016

  • The School Design Advisory Team (SDAT) process continued.
  • School tours and the geotechnical report was completed.


Return to Daniel Bagley