Planning & Construction Updates

January 2017

The schematic design phase work continues. The Site-Specific Education Specifications are being refined and the transportation study continues. Preparation for the General Contractor/Construction Manager (GCCM) procurement process was nearing completion.


December 2016

The School Design Advisory Team (SDAT) process has been completed. The schematic design phase work has begun. Site-Specific Educational Specifications are being developed. Work has begun on the transportation study. 


November 2016

The School Design Advisory Team (SDAT) process was nearly complete. The geotechnical report has been completed with the consultant comments incorporated. Work began on the transportation study. 


October 2016

The School Design Advisory Team (SDAT) process continued. School tours and the geotechnical report was completed.


Return to Daniel Bagley