Project Construction Update

Construction Update - October 2009

New Denny International Middle School Gymnasium - reinforcing steel and vapor retarder for the structural concrete slab subfloor for the new wood athletic flooring

New Denny International Middle School Gymnasium - reinforcing steel and vapor retarder for the structural concrete slab subfloor for the new wood athletic flooring

As of the end of September, 2009, the new Chief Sealth boilers are complete and awaiting the final report. The installation of the sewer line and water on the north end of the project was completed. The old Chief Sealth courtyards have been demolished and the contractor began framing walls and completing mechanical, electrical and plumbing rough-in in Chief Sealth High School.

The contractor is 80% complete with the installation of the footings for the new Galleria and Denny International Middle School and 75% complete with the underground utilities for the new Galleria. The contractor also began erecting walls for the new middle school gymnasium.

This month, October, 2009, work will continue on the foundation and walls for the new Denny International Middle School. Deliveries of the structural steel for the new Denny International Middle School will continue and steel erection of the Commons area will begin. The contractor will continue framing walls, and completing mechanical, electrical and plumbing rough-in in Chief Sealth High School. The site work will continue on the south and west sides of the project.

Please contact the Denny/Chief Sealth project manager, Robert Evans, at (206) 658-2731 or email at revans@heery.com if you have any questions or concerns regarding this construction project.

Please note - For safety reasons, visitor access is not permitted on the construction site at this time.


Construction Update - September 2009

CConcrete Pour at Building C (new Galleria) Brace Frame Footing

Concrete Pour at Building C (new Galleria) Brace Frame Footing

Last month, August, 2009, the contractor completed the sub-grade work for the new Denny International Middle School. The contractor also completed the initial work inside the existing Chief Sealth High School as well as the retaining wall along the east side of the property. The contractor completed a deep sewer tie-in into a manhole in SW Kenyon Street.

This month, September, 2009, work will continue on the foundation for the new Denny International Middle School. The site asphalt paving at the south end of the project, the parking lots and new drives, will begin and work will continue on the short aggregate pier work and deep sewer line. The contractor will also continue work on the installation of the sewer line and water on north end of the project. Structural steel for the Galleria started arriving and deliveries for the new Denny International Middle School will continue into October.

Please contact the Denny/Chief Sealth project manager, Robert Evans, at (206) 658-2731 or email at revans@heery.com if you have any questions or concerns regarding this construction project.

Please note - For safety reasons, visitor access is not permitted on the construction site at this time.


Construction Update - August 2009

Chief Sealth August 2009 Construction Update

Denny-Sealth Short Aggregate Pier drilling for the new Denny School & Galleria/Commons Foundation

Last month, July, 2009, the Project 1 contractor completed the retaining wall along the east property line as well as continued work on the sewer line along with east property. Grading for the north parking lot was started and will be completed by the first week of August.

This month, August, 2009, work for Project 1 will include site asphalt paving at the north parking lot and east road.

For Project 2, installation of the short aggregate piers will be completed by the end of this month. The Project 2 contractor is starting the interior renovation of the main classroom building for Chief Sealth. Foundation work will also be starting in August along with site work including grading, excavation and underground utilities for the new Denny school.

Installation of some storm sewer piping and connecting to the existing sanitary manhole in SW Kenyon Street, 260 feet east of the SW 26th Avenue intersection will take place August 10th through the 21st. The new utility will serve the new Denny Sealth campus scheduled to open in fall, 2010. No other utilities will be impacted by this work. Pedestrian and vehicle access to homes adjacent to the work zone will be maintained during the street closure. Detour signs will be up to direct all other traffic during construction hours.

Please contact the Denny/Chief Sealth project manager, Robert Evans, at (206) 658-2731 or email at revans@heery.com if you have any questions or concerns regarding this construction project.

Please note - For safety reasons, visitor access is not permitted on the construction site at this time.


Construction Update - July 2009

Aerial View Rendering of the completed Denny International Middle School and Chief Sealth High School showing the Galleria, green roof and new entry plaza

Aerial View Rendering of the completed Denny International Middle School and Chief Sealth High School showing the Galleria, green roof and new entry plaza

Last month, June, 2009, saw the start of grading work to prepare the foundation for the new Denny International Middle School and the new galleria. The contractor removed the remaining portables and the new gas service was turned on.

This month, July, 2009, work will continue on the foundation, utilities and the retaining walls. Work will begin on the commissioning of the new boiler as well as the installation of the improvements to Chief Sealth including electrical and mechanical upgrades to the classrooms.

Please contact the Denny/Chief Sealth project manager, Robert Evans, at (206) 658-2731 or email at revans@heery.com if you have any questions or concerns regarding this construction project.

Please note - For safety reasons, visitor access is not permitted on the construction site at this time.


Construction Update - June 2009

Aerial View Rendering of the completed Denny International Middle School and Chief Sealth High School

Aerial View Rendering of the completed Denny International Middle School
and Chief Sealth High School

The Seattle Public Schools’ Denny International Middle School and Chief Sealth High School construction project has been granted a Master Use Permit to begin major construction work. This phase of the construction work, Project 2, will begin in June and will include the construction of a new middle school and the renovation of the existing Chief Sealth High School. The co-located campus will include:

  • All newly renovated classrooms for Chief Sealth
  • A new middle school designed to support middle-school best practices
  • A new galleria/commons
  • New health center
  • Energy efficient windows, lighting and air systems
  • Structures that meet new earthquake codes
  • ADA Accessibility
  • New fire and sprinkler systems
  • New separate plazas
  • Safe off-street bus loading
  • New foreign language classrooms
  • Renovated Auditorium

Chief Sealth is scheduled for completion in summer, 2010, ready for the fall school year. Denny International Middle School is scheduled to be completed by winter, 2011.

During this phase of construction, there may be heavy equipment used along the streets immediately surrounding the construction site. There is no street work planned during initial construction activities. When street work is planned, we will provide advance notice to any neighbors that might be affected by that work.

As a parent or neighbor of the school, you may be impacted by the sights and sounds of construction. Seattle Public Schools, Denny International Middle School and Chief Sealth High School thank you for your continued support and understanding during construction.

Please contact the Denny/Chief Sealth project manager, Robert Evans, at (206) 658-2731 or email at revans@heery.com if you have any questions or concerns regarding this construction project.

Please note - For safety reasons, visitor access is not permitted on the construction site at this time.


Construction Update - May 2009

Chief Sealth May 2009 Construction Update

Installation of the Gas Line at Chief Sealth High School

 

Last month, April 2009, the remaining building pre-work construction, in addition to the gas and water lines, were completed. April also saw the beginning of preparation of mobilizing for the next phase of construction, Project 2, which includes the modernization of Chief Sealth, the construction of the new Galleria and the new Denny Middle School.

This month, May, 2009, the gas meter will be installed and the new boilers will be tested. Part of the mobilization you will see will be the Project 2 contractor bringing their trailers and equipment on site to begin work.

As a parent or neighbor of the school, you may be impacted by the sights and sounds of construction. Seattle Public Schools and Chief Sealth High School thank you for your continued support and understanding during construction.

Please contact the Denny/Chief Sealth project manager, Robert Evans, at (206) 658-2731 or email at revans@heery.com if you have any questions or concerns regarding this construction project.

Please note - For safety reasons, visitor access is not permitted on the construction site at this time.


Construction Update - April 2009

Chief Sealth April 2009 Construction Update

Boiler Room at Chief Sealth High School

Last month, March 2009, saw the completion of much of the pre-work construction at Chief Sealth High School. This phase included hazmat abatement, structural reinforcing, demolition at the Chief Sealth site and the installation of a new mechanical system including new boilers.

This month, April 2009, the remaining building pre-work construction, in addition to the gas and water lines, are scheduled to be completed. April will also see the beginning of preparation for mobilizing for the next phase of construction, which includes the modernization of Chief Sealth, the construction of the new Galleria and the new Denny Middle School.

As a parent or neighbor of the school, you may be impacted by the sights and sounds of construction. Seattle Public Schools and Chief Sealth High School thank you for your continued support and understanding during construction.

The BEX Hotline

The Building Excellence III program Hotline is routinely updated to provide you with the most current information and activities about your school of interest: please dial (206) 368-4082 and press 6 for current information regarding the Chief Sealth renovation.

Please contact the Denny/Chief Sealth project manager, Robert Evans, at (206) 658-2731 or email at revans@heery.com if you have any questions or concerns regarding this construction project.

Please note - For safety reasons, visitor access is not permitted on the construction site at this time.


Construction Update - March 2009

Chief Sealth Completed Auditorium Shearwall

This month, March 2009, construction pre-work at Chief Sealth High School will include the installation of a new gas service line.  Part of this work will entail constructing a temporary trench on or adjacent to the pedestrian pathway on the east side of the sports fields.  

Other winter construction work will include:

  • Removal of Existing Utility Lines
  • Installation of a New Mechanical System Including New Boilers
  • Installation of a New Water Line

As a parent or neighbor of the school, you may be impacted by the sights and sounds of construction. Seattle Public Schools and Chief Sealth High School thank you for your continued support and understanding during construction.  

Construction Services Bidding

In February 2009, bidding for the next phase of construction will begin for both Chief Sealth High School and the New Denny Middle school. The scope of the work includes construction of the new commons with a health center, kitchen, new middle school gymnasium and classroom building as well as other site and landscaping improvements.

For contractors who are interested in learning more about the bid dates for this phase, please visit the Builders Exchange at: http://www.bxwa.com/1280.html

Questions?

Please contact the Chief Sealth project manager, Robert Evans, at (206) 658-2731 or email at revans@heery.com if you have any questions or concerns regarding this construction project.

Please note - For safety reasons, visitor access is not permitted on the construction site at this time.


Construction Update - February 2009

Exterior Construction Continues

 

Last month, work on the Chief Sealth construction site included the completion of the hazardous waste removal and demolition activities as well as the seismic (earthquake) upgrades to the gymnasium.  The construction of the new auditorium roof was also completed.

This month, February 2009, construction work will include:

  • Completion of all exterior and interior concrete shear walls
  • Installation of wall reinforcement (strong-backing by using steel tube)
  • Installation of a new mechanical system including new boilers
  • Removal of existing utility lines
  • Installation of new domestic water line

Construction Services Bidding

In February 2009, bidding for the next phase of construction will begin for both Chief Sealth High School and the New Denny Middle school. The scope of the work includes construction of the new commons with a health center, kitchen, new middle school gymnasium and classroom building as well as other site and landscaping improvements.

For contractors who are interested in learning more about the bid dates for this phase, please visit the Builders Exchange at: http://www.bxwa.com/1280.html

Questions?

Please contact the Chief Sealth project manager, Robert Evans, at (206) 658-2731 or email at revans@heery.com if you have any questions or concerns regarding this construction project.

Please note - For safety reasons, visitor access is not permitted on the construction site at this time.


Construction Update - January 2009

Shearwall in the Making

Construction on the Chief Sealth High School project is ongoing and work on hazardous material removal, demolition and seismic upgrades is almost complete.

This month, construction will include:

  • Installation of a new mechanical system
  • Installation of new offsite utilities
  • Completion of new shear walls
  • Completion of the new auditorium roof.

The Seattle Public Schools wishes to thank the surrounding neighborhood for continued support and understanding during construction.


Fall 2008 Construction Update

The first phase of renovations of Chief Sealth High School began this past July. As a neighbor of the school, or a parent, we realize you may be impacted by the sights and sounds of construction, and appreciate your understanding.

Work in fall 2008 will include:

  • Installing a construction fence around the entire school
  • Demolishing old portables
  • Installing new seismic upgrades in existing buildings
  • Removing existing mechanical system
  • Removing old asphalt around gymnasium
  • Removing old tennis courts and softball field
  • Installing new site utilities

The Seattle Public Schools wishes to thank the surrounding neighborhood for continued support and understanding during construction.